The Supreme Court dismissed GMADA’s petition in diary 56518/2026. The underlying dispute concerns land compensation for the Boothgarh–Togan road.

The order dated 2 November and signed on 3 November deals separately with connected petitions. It lists two groups for 16 November. Their inclusion in the same order does not decide them all.

What it means for your next step.

Landowners following this litigation should match the diary number and the underlying award to their own case.

Supporting sources

Check before acting

Read the complete original document, then check for later notices, corrections and project-specific records. This editorial summary is not a legal determination, a current availability statement or an invitation to book.

Supreme Court order via Indian Kanoon ↗

Source: Supreme Court order via Indian Kanoon. Editorial check: 9 November 2026. Event and document dates are labelled separately. Developer statements are attributed, not independently certified.