What the source says.
A publicly dated site record from 1 October describes Highland Mayfields’ fourteenth floor as nearly complete, alongside sample-flat finishing. The observation comes from a property adviser and site staff, rather than a certified engineer’s report or confirmation of possession readiness.
A 1 October site record provides a recent construction checkpoint for Highland Mayfields in Sector 118, Mohali.
Fidus Realty’s public progress page describes the fourteenth floor as nearly complete and records finishing work in a sample flat. It also distinguishes the two towers being built from a third tower planned for a later stage.
The evidence has an important limit: Fidus says floor counts come from site staff and are not measurements derived from photographs or a statement issued by the developer. Its dated record is therefore useful supporting material, rather than an independent certification of the structure or the entire project’s completion percentage.
Buyers visiting the site can make that distinction practical. Ask which tower and floor the update refers to, compare it with the unit in the agreement, and request a current written construction schedule. A furnished or nearly finished sample apartment does not establish that the purchased home, lifts, common services and statutory documentation are ready together.
What it means for your next step.
This is a 1 October observation retained under its original date, not a new event on 9 October. No handover announcement or revised contractual completion date has been verified for this article. The next useful update would connect tower-specific construction progress with remaining services and approvals.
Reading the dates correctly
Site visit dated 1 October; separate publication date not established. Floor count is attributed to site staff. Exact phase approval/current registration, completion and possession not independently verified. Competitor price quotes excluded.
Supporting sources
Check before acting
Read the complete original document, then check for later notices, corrections and project-specific records. This editorial summary is not a legal determination, a current availability statement or an invitation to book.
Dated property-adviser site record ↗Source: Fidus Realty. Editorial check: 9 October 2026. Event and document dates are labelled separately. Developer statements are attributed, not independently certified.