Promoter Details (Other Than Individual)
| Jubilee Joy Homes LLP | Limited Liabilities Partnership | ||
| Main Objects of Organization | To carry on the Business of Builders and developers of residential plots, flats and office spaces or to acquire, purchase & develop and Construct / reconstruct residential or commercial unit(s) thereon either singly or jointly or in partnership with others, for sale or for earning rental income there from. | ||
| Registered Address of Organization |
701- 728, 7th Floor, Jubilee Walk, Sector 70
,
Sector 70, Jubilee Walk
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160071 |
||
| Official Address |
701- 728, 7th Floor, Jubilee Walk, Sector 70
,
Sector 70, Jubilee Walk
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160071 |
||
| 8 (in years) | 0 (in years) | ||
| WebLink (Promoter/Parent-Entity) | Not Available | ||
Organization Member Details (If Applicable)
| Sr.No | Designation | Name of Member | Official Address | View Photograph |
|---|---|---|---|---|
| 1 | Designated Partner | Baljeet Singh |
#2459, Phase 10
,
Sector 64,
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160062 Email: baljeet[at]jubileegroup.in |
|
| 2 | Designated Partner | Jagmohan Garg |
#747, Sector 8 B
,
Sector 8 B
Chandigarh , Chandigarh - 160009 Email: jagmohan[at]jubileegroup.in |
|
| 3 | Designated Partner | Sanyam Dudeja |
# 1959
,
Sector 64,
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160062 Email: sanyam[at]jubileegroup.in |
|
| 4 | Designated Partner | Sukhwant Singh |
House No. 160, Sector 9 B
,
House No. 160, Sector 9 B
Chandigarh , Chandigarh - 160009 Email: sukhwant[at]jubileegroup.in |
|
Details and Profile of On-Going and Completed Projects in Past Five Years or since Inception
| Sr.No | Project Name | Project Status | Area Constructed (in Sqr mtr) | Project Start Date | Original Proposed Date of Complete | Actual Complete Date |
|---|---|---|---|---|---|---|
| 1 | Jubilee Walk | On-going | 35461.11 | 09-Dec-2018 | 31-Dec-2023 | 30-Jun-2024 |
| 2 | Jubilee Juncttion | On-going | 9240.27 | 28-Mar-2019 | 31-Mar-2022 | 30-Sep-2022 |
| 3 | Jubilee City Gardens | On-going | 93257.35 | 01-Mar-2022 | 31-Mar-2025 | 31-Mar-2025 |
| 4 | Jubilee Parklane | On-going | 101233.42 | 18-Jul-2022 | 18-Jul-2025 | 18-Jul-2025 |
| 5 | Jubilee CLIO | On-going | 7998.9 | 19-Dec-2022 | 31-Aug-2026 | 25-Jan-2029 |
| 6 | Jubilee Westgrove | On-going | 25762.29 | 30-Jul-2024 | 30-Jun-2027 | 30-Jul-2029 |
| 7 | Jubilee Parklane Extension | On-going | 312325 | 06-Sep-2024 | 17-Jul-2027 | 17-Jul-2027 |
| 8 | Jubilee Techyards | On-going | 1533704 | 01-Dec-2025 | 29-Dec-2029 | 30-Dec-2029 |
Litigation(s) related to Past Projects
| Sr.No | Project Name | Case Title | Case Number | Authority/Forum Name where case is Pending/Resolved |
|---|---|---|---|---|
| 1 | Jubilee Parklane | Balvinder Brar v/s Jubilee Joy Homes | GC 0388/ 2024 | In the Court Of Honorable Chairman in RERA |
| 2 | Jubilee Techyards | Notice u/s 59 | Nill | In the Court Of Honorable Chairman in RERA |
About the Project
| Project Name | Jubilee Twinto | ||
| Project Address |
Jubilee Twinto, Sec-112,SAS Nagar Village Bairampur , Teh. Mohali
,
Sec-112,SAS Nagar Village Bairtampur , Teh. Mohali
Mohali , Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140307 |
||
| Project Amenities | Service Apartments, Road Network, Parking Area, Sewerage, Street Light, STP, Water Supply Network, Disposal Network, Electricity Network will be facilitated in the project. | ||
| Project Zone | Zone 1 - Master Plan Area of S.A.S. Nagar, New Chandigarh and Zirakpur. | ||
| Type of Project |
(1) Commercial (Building/Tower Development) |
||
| Project Status | New Project | Project Cost (in rupees) | 1262400000.00 (INR) |
| Project Start Date | 17-Sep-2025 | Proposed/ Expected Date of Project Completion as specified in Form B | 30-Mar-2031 |
| Project Web Link | www.jubileegroup.in | Mega Project (Yes/No) | No |
| Specification Details of Proposed Project as per the Brochure/ Prospectus |
:-
RCC Frame Structure :- Premium Vertified Flooring & Antiskide in Toilete and Bathroom :- Plastic Emulsion :- Branded CP Fittings :- Modular Switch Sockets :- Kitchen with Hob |
||
| Authorized Person for Communication with regards to Project |
Baljeet
Singh
701- 728, 7th Floor, Jubilee Walk, Sector 70 , Sector 70 Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160071 E-Mail: liaison[at]jubileegroup.in Mobile Phone: 6283361063 |
||
Bank Account Details of the Special/Separate Account to be maintained in a Schedule Bank
| Bank Name | HDFC Bank Limited | Branch Name | Chandigarh sector 35 b |
| Bank Account Number | Account number omitted from this archived copy; consult the authority source. | Bank IFSC Code | HDFC0000450 |
| Account Holder Name | JBL JOY HMS LLP JBL TWINTO AC RERA | ||
| Bank Address |
SCO Site no 371 & 372
,
SECTOR 35B
Chandigarh , Chandigarh - 160035 |
||
Project Land Details
| 14706.154 (in sqr mtrs) | |||
| 14706.154 (in sqr mtrs) | 0 (in sqr mtrs) | ||
| 0 (in sqr mtrs) | 0 (in sqr mtrs) | ||
| 1809.435 (in sqr mtrs) | 0 (in sqr mtrs) | ||
| 12896.719 (in sqr mtrs) | |||
Project Land Khasra(s) and Area Details
| SrNo | Khasra Number of Land proposed to be developed | Area of Land proposed under Khasra | Name of Villages under Khasra | Project Land Status |
|---|---|---|---|---|
| 1 | 10//23/1 | 123.202 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 2 | 10//19 | 2317.218 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 3 | 10//22/1 | 2225.784 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 4 | 10//22/2 | 539.221 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 5 | 10//20 | 505.86 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 6 | 10//11 | 1770.51 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 7 | 10//23/2 | 741.844 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 8 | 10//12 | 2317.218 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 9 | 10//17 | 665.56 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 10 | 23//3/3 | 588.062 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 11 | 10//24 | 2867.847 (in sqr mtrs) | Bairampur | Owned By Promoter |
| 12 | 23//3/2 | 44.263 (in sqr mtrs) | Bairampur | Owned By Promoter |
Project Plan(s)
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 2 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 3 | Approved Project Site OR Location Map | -- | -- |
Open official attachment ↗
|
| 4 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 5 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 6 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 7 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 8 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 9 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 10 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 11 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 12 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 13 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 14 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 15 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 16 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 17 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 18 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 19 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
Proforma of documents to be signed with Allottees
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Pro forma Agreement of Sale to be signed with allottees | -- | -- |
Open official attachment ↗
|
| 2 | Pro forma of Allotment Letter to be provided to allottees | -- | -- |
Open official attachment ↗
|
| 3 | Pro forma of Conveyance Deed to be signed with allottees | -- | -- |
Open official attachment ↗
|
Project Documents
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Authenticated Copy of Form B | -- | -- |
Open official attachment ↗
|
| 2 | CA Certificate (Form 3) | -- | -- |
Open official attachment ↗
|
| 3 | CA Certificate (Form 3) | -- | -- |
Open official attachment ↗
|
| 4 | CA Certificate (Form 3) | -- | -- |
Open official attachment ↗
|
| 5 | Proforma for Undertaking- cum-Indemnity Bond | -- | -- |
Open official attachment ↗
|
| 6 | Proforma for Undertaking- cum-Indemnity Bond | -- | -- |
Open official attachment ↗
|
Project Approvals Document(s)
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | AAI Height NOC from Civil Aviation Department/ Airport Authority | Approvals (Received) | 31-Mar-2023 |
Open official attachment ↗
|
| 2 | CLU Certificate | -- | -- |
Open official attachment ↗
|
| 3 | Copy of Registration as Promoter | -- | -- |
Open official attachment ↗
|
| 4 | Electric Substation NOC | Approvals (Received) | 13-Nov-2024 |
Open official attachment ↗
|
| 5 | Environment Clearance certificate/ NOC | Approvals (Received) | 25-Sep-2023 |
Open official attachment ↗
|
| 6 | License as Promoter from competent Authority | Approvals (Received) | 09-Mar-2023 |
Open official attachment ↗
|
| 7 | License to develop colony or society from Competent Authority | -- | -- |
Open official attachment ↗
|
| 8 | NOC from Fire Department/ Chief Fire Officer | Approvals (Received) | 15-Apr-2025 |
Open official attachment ↗
|
| 9 | NOC from NHAI/ PWD | Approvals (Received) | 22-Apr-2025 |
Open official attachment ↗
|
| 10 | Other Document (DE hypothecation of service apartment approval) | Approvals (Received) | 10-Jul-2025 |
Open official attachment ↗
|
| 11 | Other Document (Drainage NOC Approved) | Approvals (Received) | 08-Mar-2022 |
Open official attachment ↗
|
| 12 | Other Document (ECBC Report From PEDA Approved) | Approvals (Received) | 15-May-2025 |
Open official attachment ↗
|
| 13 | Other Document (Explanation regarding project name J Twinto) | Legal Documents (Revised) | 14-Oct-2025 |
Open official attachment ↗
|
| 14 | Other Document (Forest NOC Khasra No's Marked of J. Twinto) | Approvals (Received) | 07-Feb-2022 |
Open official attachment ↗
|
| 15 | Other Document (Hypothecation of service apartment letter by GMADA) | Legal Documents (Received) | 11-Jun-2024 |
Open official attachment ↗
|
| 16 | Other Document (Inventory Details) | Legal Documents (Received) | 22-Oct-2025 |
Open official attachment ↗
|
| 17 | Other Document (Jubilee Westgrove Approved RERA) | Approvals (Received) | 30-Aug-2024 |
Open official attachment ↗
|
| 18 | Other Document (KYC Aadhar Card and Pan Card of Promoters) | Legal Documents (Received) | 13-Oct-2025 |
Open official attachment ↗
|
| 19 | Other Document (Provisinal FY statement 2024 to 2025 with Circular) | Legal Documents (Received) | 22-Oct-2025 |
Open official attachment ↗
|
| 20 | Other Document (Reply of observation dated 08.10.2025) | Legal Documents (Revised) | 14-Oct-2025 |
Open official attachment ↗
|
| 21 | Other Document (Reply of observation dated 17.10.2025) | Legal Documents (Revised) | 22-Oct-2025 |
Open official attachment ↗
|
| 22 | Pollution Clearance from Punjab Pollution Control Board | Approvals (Received) | 12-Mar-2025 |
Open official attachment ↗
|
Project Land Documents
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Land Title Search Report | -- | -- |
Open official attachment ↗
|
| 2 | Latest Jamabandi Document | -- | -- |
Open official attachment ↗
|
| 3 | Legal Title Deed(s) - In case Land is owned by Promoter | -- | -- |
Open official attachment ↗
|
| 4 | Non Encumbrance Certificate | -- | -- |
Open official attachment ↗
|
| 5 | Non Encumbrance Certificate | -- | -- |
Open official attachment ↗
|
| 6 | Project Land Khasra Report or Plan | -- | -- |
Open official attachment ↗
|
| 7 | Project Land Khasra Report or Plan | -- | -- |
Open official attachment ↗
|
Project Brochure/ Prospectus Documents
| Sr.No | Document Name | View Details |
|---|---|---|
| 1 | Advertisement and Brochure/ Prospectus |
Open official attachment ↗
|
Type of Project (Jubilee Twinto)
| 1 | Commercial ( Building/Tower Development ) |
Project Building/ Tower/ Block Construction & Inventory Details
| Sr.No | Building/Tower/Block Name | Number of Floor/Plots related to Building/ Tower/ Block | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | JUBILEE TWINTO |
Number of Floor/Plots Currently Sanctioned:
14
Number of Floor/Plots Proposed: 14 Number of Floors Constructed: 0 |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Parking Details
| Sr.No | Type of Parking | Total Area of Parking Space | Total Number of Parking Space | No of Parking Space Booked or Sold |
|---|---|---|---|---|
| 1 | Basement | 4606.311 (in sqr Mtrs) | 144 | 0 |
| 2 | Open | 3253.114 (in sqr Mtrs) | 141 | 0 |
Internal Infrastructure and Facilities Details
| Sr.No | Internal Infrastructure Facilities Name | Internal Infrastructure Facilities Details | Work Progress % Percentage |
|---|---|---|---|
| 1 | Fire Fighting | Yet to Start | 0.00 |
| 2 | Drinking Water | Yet to Start | 0.00 |
| 3 | Rain Water Harvesting | Yet to Start | 0.00 |
| 4 | Street Lighting | Yet to Start | 0.00 |
| 5 | Internal Roads and Foot Path | Yet to Start | 0.00 |
| 6 | Sewearge Line Internal | Yet to Start | 0.00 |
| 7 | Storm Water Drainage | Yet to Start | 0.00 |
| 8 | Solid Waste Management and Disposal | Yet to Start | 0.00 |
| 9 | Electricity Supply Transformer and Sub Station | Yet to Start | 0.00 |
External Infrastructure and Facilities Details
| Sr.No | External Infrastructure Facilities Name | Facilities Type | External Infrastructure Facilities Details | Work Progress %age |
|---|---|---|---|---|
| 1 | External Roads and Road System Landscaping | External Development Work | Access of the project is already existing NH. | 0.00 |
| 2 | Water Supply System | Self-Development | Yet to Start | 0.00 |
| 3 | Sewerage and Drainage System | External Development Work | Yet to Start | 0.00 |
| 4 | Electricity Supply Transformer and Sub Station | Self-Development | Yet to Start | 0.00 |
| 5 | Solid Waste Management and Disposal | Self-Development | Yet to Start | 0.00 |
Project Professionals (Real Estate Agents, Structural Engineer, Architect, Contractors and other person)
| Sr.No | Name of Professional | Associated Consultant Type | Name & Year of Establishment of Promoter | Name & Profile of Key Projects Completed |
|---|---|---|---|---|
| 1 | JASPREET SINGH |
Architect
CA-2013-60962 |
Architects and Engineers established in 2013 | Dayal constructions, Ware House |
| Address for Official Communication |
H. No. 352, FF, Gillico Valley, Sector- 127, Kharar, SAS Nagar
,
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140301 Email: ar.jtsandhu[at]gmail.com Mobile/Landline Number: 9911055032 |
|||
| 2 | VIKAS KAUSHAL |
Structural Engineer
M-138341-2 |
Architects and Engineers established in 2009 | Jubilee Golfvista, Jubilee City Gardens, Jubilee Parklane, Jubilee Walk |
| Address for Official Communication |
SCO 1241, Sector 5, Panchkula
,
SCO 1241, Sector 5, Panchkula
Panchkula , Haryana - 134114 Email: sascengineers[at]gmail.com Mobile/Landline Number: 9501753617 |
|||
| 3 | CA DEEPAK JINDAL |
Chartered Accountant
FRN023023N |
CA Deepak Jindal , Year of Establishment 1996 | Jubilee Junction, Jubilee Square, RS Infra |
| Address for Official Communication |
Unit A-203, Second Floor
,
Elante Mall
Chandigarh , Chandigarh - 160002 Email: cadeepakjindal[at]gmail.com Mobile/Landline Number: 9888024485 |
|||
Quarterly Updates of Registered Project
| Sr.No. | Quarter Name | Quarter Year | Reference Number | Reference Date | View Details |
|---|---|---|---|---|---|
| 1 | QTR-IV (October-December) | 2025 | QUP2025L20260784 | 01-Feb-2026 | Open official attachment ↗ |
| 2 | QTR-I (January-March) | 2026 | QUP2026F20261844 | 18-Apr-2026 | Open official attachment ↗ |
| 3 | QTR-II (April-June) | 2026 | QUP2026S20263924 | 27-Jul-2026 | Open official attachment ↗ |
Open official attachment ↗