Promoter Details (Other Than Individual)
| VAMANA DEVELOPERS | Partnerships | ||
| Main Objects of Organization | REAL ESTATE BUSINESS | ||
| Registered Address of Organization |
SCO No.44 ,First Floor, Cabin no. 2,Block E, Aerocity Jubilee Square , Airport Road
,
SAS Nagar , Mohali
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160055 |
||
| Official Address |
SCO No.44 ,First Floor, Cabin no. 2,Block E, Aerocity Jubilee Square , Airport Road
,
SAS Nagar , Mohali
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 160055 |
||
| 0 (in years) | 0 (in years) | ||
| WebLink (Promoter/Parent-Entity) | |||
Organization Member Details (If Applicable)
| Sr.No | Designation | Name of Member | Official Address | View Photograph |
|---|---|---|---|---|
| 1 | PARTNER | RITESH NARULA |
#941 ATS GOLF MEADOWS PRELUDE BARWALA ROAD
,
SAS Nagar , Mohali
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140507 Email: narularp[at]gmail.com |
|
| 2 | PARTNER | RAVI SHARMA |
C/o Pawan Kumar Sharma H no. B-10, GF-01, Nirmal Chaya Tower Lohgarh
,
Zirakpur
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140603 Email: ravis29dec[at]gmail.com |
|
| 3 | PARTNER | AMIT GULATI |
C/o ANIL GULATI , HOUSE NO. 17, BLOCK-D , WAVE ESTATE
,
SECTOR 85 SOHANA SAS NAGAR MOHALI
Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140308 Email: gulati44[at]yahoo.com |
|
| 4 | PARTNER | RANBIR BANSAL |
PLOT NO. 43 , INDUSTRIAL AREA , WARD NO. 16 , CHEEKA , KAITHAL
,
HARYANA
Kaithal , Haryana - 136034 Email: drranbir21[at]gmail.com |
|
| 5 | PARTNER | VIPIN SINGLA |
#1116, Sector 12-A , Panchkula
,
Panchkula , Haryana
Panchkula , Haryana - 134112 Email: vipinsingla[at]gopalenterprises.net |
|
Litigation(s) related to Past Projects
| Sr.No | Project Name | Case Title | Case Number | Authority/Forum Name where case is Pending/Resolved |
|---|---|---|---|---|
| -- | -- | -- | -- | -- |
About the Project
| Project Name | VAMANA ARVINDAM | ||
| Project Address |
Revenue Estate of Nabha, Sub-tehsil Zirakpur , Tehsil -Dera Bassi
,
Distt.SAS Nagar ,Punjab
Dera Bassi , Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140603 |
||
| Project Amenities | Electricity supply , Street Lightning , Water Supply, STP , Drainage etc. | ||
| Project Zone | Zone 1 - Master Plan Area of S.A.S. Nagar, New Chandigarh and Zirakpur. | ||
| Type of Project |
(1) Residential (Building/Tower Development) |
||
| Project Status | New Project | Project Cost (in rupees) | 1091420000.00 (INR) |
| Project Start Date | 22-May-2024 | Proposed/ Expected Date of Project Completion as specified in Form B | 05-May-2029 |
| Litigation(s) related to Project | Nil | Mega Project (Yes/No) | No |
| Specification Details of Proposed Project as per the Brochure/ Prospectus |
:-
MIVAN :- TILES :- RCC :- KOHLER :- L & T :- MODULAR |
||
| Authorized Person for Communication with regards to Project |
RAVI
SHARMA
House no. B-10, Ground Floor -01 , Nirmal Chhaya Tower , Logharh , Zirakpur ,SAS Nagar , Mohali Sahibzada Ajit Singh Nagar (Mohali) , Punjab - 140603 E-Mail: ravi29dec[at]gmail.com Mobile Phone: 8054500799 |
||
Bank Account Details of the Special/Separate Account to be maintained in a Schedule Bank
| Bank Name | HDFC Bank Limited | Branch Name | HDFC Bank Limited |
| Bank Account Number | Account number omitted from this archived copy; consult the authority source. | Bank IFSC Code | HDFC0000154 |
| Account Holder Name | VAMANA DEVELOPERS RERA ACCOUNT | ||
| Bank Address |
HDFC BANK LIMITED , BRAR COMPLEX, ZIRAKPUR - PATIALA HIGHWAY
,
DISTT. MOHALI , ZIRAKPUR
Amritsar , Punjab - 140603 |
||
Project Land Details
| 25648 (in sqr mtrs) | |||
| 0 (in sqr mtrs) | 25648 (in sqr mtrs) | ||
| 5001.081 (in sqr mtrs) | 0 (in sqr mtrs) | ||
| 0 (in sqr mtrs) | 0 (in sqr mtrs) | ||
| 18999.638 (in sqr mtrs) | |||
Project Land Khasra(s) and Area Details
| SrNo | Khasra Number of Land proposed to be developed | Area of Land proposed under Khasra | Name of Villages under Khasra | Project Land Status |
|---|---|---|---|---|
| 1 | 1077/693 | 2927.5 (in sqr mtrs) | Village Nabha, Zirakpur | Not Owned By Promoter |
| 2 | 694 | 3345.72 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 3 | 695 | 3345.72 (in sqr mtrs) | Village Nabha, Zirakpur | Not Owned By Promoter |
| 4 | 696 | 3345.72 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 5 | 1137/686 | 2425.65 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 6 | 689 | 3345.72 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 7 | 690/1 | 1923.79 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 8 | 688/2 | 480.947 (in sqr mtrs) | Village Nabha , Zirakpur | Not Owned By Promoter |
| 9 | 697 | 3011.15 (in sqr mtrs) | Village Nabha, Zirakpur | Not Owned By Promoter |
| 10 | 698 | 1505.57 (in sqr mtrs) | Village Nabha, Zirakpur | Not Owned By Promoter |
Project Plan(s)
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 2 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 3 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 4 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 5 | Approved Layout Plan | -- | -- |
Open official attachment ↗
|
| 6 | Approved Project Site OR Location Map | -- | -- |
Open official attachment ↗
|
| 7 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 8 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 9 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 10 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 11 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 12 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 13 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 14 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 15 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 16 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 17 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 18 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 19 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 20 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 21 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 22 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 23 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 24 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 25 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 26 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
| 27 | Sanctioned Building Plan | -- | -- |
Open official attachment ↗
|
Proforma of documents to be signed with Allottees
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Pro forma Agreement of Sale to be signed with allottees | -- | -- |
Open official attachment ↗
|
| 2 | Pro forma of Allotment Letter to be provided to allottees | -- | -- |
Open official attachment ↗
|
| 3 | Pro forma of Conveyance Deed to be signed with allottees | -- | -- |
Open official attachment ↗
|
Project Documents
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Authenticated Copy of Form B | -- | -- |
Open official attachment ↗
|
| 2 | CA Certificate (Form 3) | -- | -- |
Open official attachment ↗
|
| 3 | Proforma for Undertaking- cum-Indemnity Bond | -- | -- |
Open official attachment ↗
|
| 4 | Proforma for Undertaking- cum-Indemnity Bond | -- | -- |
Open official attachment ↗
|
Project Approvals Document(s)
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | AAI Height NOC from Civil Aviation Department/ Airport Authority | Approvals (Received) | 15-Mar-2023 |
Open official attachment ↗
|
| 2 | CLU Certificate | -- | -- |
Open official attachment ↗
|
| 3 | Copy of Registration as Promoter | -- | -- |
Open official attachment ↗
|
| 4 | Copy of Registration as Promoter | -- | -- |
Open official attachment ↗
|
| 5 | Electric Substation NOC | Approvals (Applied) | 21-May-2024 |
Open official attachment ↗
|
| 6 | Environment Clearance certificate/ NOC | Approvals (Received) | 15-Jan-2024 |
Open official attachment ↗
|
| 7 | License as Promoter from competent Authority | Approvals (Received) | 21-Apr-2023 |
Open official attachment ↗
|
| 8 | License as Promoter from competent Authority | Approvals (Received) | 23-Jan-2023 |
Open official attachment ↗
|
| 9 | License to develop colony or society from Competent Authority | -- | -- |
Open official attachment ↗
|
| 10 | NOC from Fire Department/ Chief Fire Officer | Approvals (Received) | 11-Jul-2023 |
Open official attachment ↗
|
| 11 | NOC from NHAI/ PWD | Approvals (Received) | 04-Mar-2024 |
Open official attachment ↗
|
| 12 | Other Document (AFFIDAVIT REGARDING NOCs) | Legal Documents (Received) | 07-May-2024 |
Open official attachment ↗
|
| 13 | Other Document (AUTHORITY LETTER) | Legal Documents (Received) | 22-Apr-2024 |
Open official attachment ↗
|
| 14 | Other Document (DRAINAGE NOC) | Approvals (Received) | 13-Oct-2023 |
Open official attachment ↗
|
| 15 | Other Document (Fire Noc ) | Approvals (Received) | 07-Nov-2023 |
Open official attachment ↗
|
| 16 | Other Document (FOREST NOC) | Approvals (Received) | 16-Apr-2024 |
Open official attachment ↗
|
| 17 | Other Document (NOC for construction of building ) | Approvals (Received) | 27-Nov-2024 |
Open official attachment ↗
|
| 18 | Other Document (NOC for Extraction of ground water ) | Approvals (Received) | 10-Apr-2024 |
Open official attachment ↗
|
| 19 | Other Document (Solid waste and Construction and Demolation waste) | Approvals (Received) | 26-Jun-2023 |
Open official attachment ↗
|
| 20 | Other Document (TREATED WASTE WATER NOC) | Approvals (Received) | 26-Jun-2023 |
Open official attachment ↗
|
| 21 | Pollution Clearance from Punjab Pollution Control Board | Approvals (Received) | 16-Oct-2023 |
Open official attachment ↗
|
| 22 | Pollution Clearance from Punjab Pollution Control Board | Approvals (Received) | 10-Jul-2024 |
Open official attachment ↗
|
Project Land Documents
| Sr.No | Document Name | Reference Number | Issue Date | View PDF |
|---|---|---|---|---|
| 1 | Collaboration or Joint Development Agreement | -- | -- |
Open official attachment ↗
|
| 2 | Consent details of actual owner of Land | -- | -- |
Open official attachment ↗
|
| 3 | Details of Encumbrances over the land | -- | -- |
Open official attachment ↗
|
| 4 | Details of Encumbrances over the land | -- | -- |
Open official attachment ↗
|
| 5 | Details of Encumbrances over the land | -- | -- |
Open official attachment ↗
|
| 6 | Land Title Deed(s) - In case land is not owned by Promoter | -- | -- |
Open official attachment ↗
|
| 7 | Land Title Deed(s) - In case land is not owned by Promoter | -- | -- |
Open official attachment ↗
|
| 8 | Land Title Search Report | -- | -- |
Open official attachment ↗
|
| 9 | Project Land Khasra Report or Plan | -- | -- |
Open official attachment ↗
|
| 10 | Project Land Khasra Report or Plan | -- | -- |
Open official attachment ↗
|
Project Brochure/ Prospectus Documents
| Sr.No | Document Name | View Details |
|---|---|---|
| 1 | Advertisement and Brochure/ Prospectus |
Open official attachment ↗
|
Type of Project (VAMANA ARVINDAM)
| 1 | Residential ( Building/Tower Development ) |
Project Building/ Tower/ Block Construction & Inventory Details
| Sr.No | Building/Tower/Block Name | Number of Floor/Plots related to Building/ Tower/ Block | ||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | BLOCK 2 |
Number of Floor/Plots Currently Sanctioned:
15
Number of Floor/Plots Proposed: 15 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 2 | BLOCK 3 |
Number of Floor/Plots Currently Sanctioned:
15
Number of Floor/Plots Proposed: 15 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 3 | BLOCK 4 |
Number of Floor/Plots Currently Sanctioned:
16
Number of Floor/Plots Proposed: 16 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 4 | BLOCK 5 |
Number of Floor/Plots Currently Sanctioned:
16
Number of Floor/Plots Proposed: 16 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 5 | BLOCK 6 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 6 | BLOCK 7 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 7 | BLOCK 8 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 8 | BLOCK 9 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 9 | BLOCK 10 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
| 10 | BLOCK 11 |
Number of Floor/Plots Currently Sanctioned:
18
Number of Floor/Plots Proposed: 18 Number of Floors Constructed: 0 |
||||||||||||||
|
||||||||||||||||
Parking Details
| Sr.No | Type of Parking | Total Area of Parking Space | Total Number of Parking Space | No of Parking Space Booked or Sold |
|---|---|---|---|---|
| 1 | Basement | 19864.744 (in sqr Mtrs) | 620 | 0 |
| 2 | Open | 5359.472 (in sqr Mtrs) | 233 | 0 |
Internal Infrastructure and Facilities Details
| Sr.No | Internal Infrastructure Facilities Name | Internal Infrastructure Facilities Details | Work Progress % Percentage |
|---|---|---|---|
| 1 | Fire Fighting | Fire Fighting | 0.00 |
| 2 | Drinking Water | Drinking Water | 0.00 |
| 3 | Rain Water Harvesting | Rain Water Harvesting | 0.00 |
| 4 | Street Lighting | Street Lighting | 0.00 |
| 5 | Club House | Club House | 0.00 |
| 6 | Park | Park | 0.00 |
External Infrastructure and Facilities Details
| Sr.No | External Infrastructure Facilities Name | Facilities Type | External Infrastructure Facilities Details | Work Progress %age |
|---|---|---|---|---|
| 1 | External Roads and Road System Landscaping | Self-Development | External Roads and Road System Landscaping | 0.00 |
| 2 | Electricity Supply Transformer and Sub Station | Self-Development | Electricity Supply | 0.00 |
| 3 | Water Supply System | Self-Development | Water Supply | 0.00 |
| 4 | Sewerage and Drainage System | Self-Development | Sewerage and Drainage System | 0.00 |
| 5 | Solid Waste Management and Disposal | Self-Development | Solid Waste Management and Disposal | 0.00 |
Project Professionals (Real Estate Agents, Structural Engineer, Architect, Contractors and other person)
| Sr.No | Name of Professional | Associated Consultant Type | Name & Year of Establishment of Promoter | Name & Profile of Key Projects Completed |
|---|---|---|---|---|
| 1 | TIRPAT GIRDHAR |
Architect
CA 2009 44080 |
2009 | HERMITAGE CENTRALIS , GREEN LOTUS , ATLANTIS 360 ETC |
| Address for Official Communication |
SC0 230-231 , THIRD FLOOR, SECTOR 34-A
,
CHANDIGARH
Chandigarh , Chandigarh - 160022 Email: aretedesignstudiochd[at]gmail.com Mobile/Landline Number: 9876046570 |
|||
Quarterly Updates of Registered Project
| Sr.No. | Quarter Name | Quarter Year | Reference Number | Reference Date | View Details |
|---|---|---|---|---|---|
| 1 | QTR-III (July-September) | 2024 | QUP2024T20242676 | 15-Oct-2024 | Open official attachment ↗ |
| 2 | QTR-IV (October-December) | 2024 | QUP2024L20250213 | 11-Jan-2025 | Open official attachment ↗ |
| 3 | QTR-I (January-March) | 2025 | QUP2025F20251060 | 08-Apr-2025 | Open official attachment ↗ |
| 4 | QTR-II (April-June) | 2025 | QUP2025S20252032 | 10-Jul-2025 | Open official attachment ↗ |
| 5 | QTR-III (July-September) | 2025 | QUP2025T20253568 | 09-Oct-2025 | Open official attachment ↗ |
| 6 | QTR-IV (October-December) | 2025 | QUP2025L20262094 | 05-May-2026 | Open official attachment ↗ |
| 7 | QTR-I (January-March) | 2026 | QUP2026F20262095 | 05-May-2026 | Open official attachment ↗ |
| 8 | QTR-II (April-June) | 2026 | QUP2026S20263542 | 15-Jul-2026 | Open official attachment ↗ |
Open official attachment ↗